Walsall Borough Housing Strategy 2026 - Risk management

Delivering the ambitions of Building Walsall 2040 requires proactive, systematic management of risks across all objectives and actions. A robust risk management framework is embedded in our strategy to identify, assess, mitigate, and monitor risks that could affect delivery, outcomes, or value for money. 

Key principles underpinning risk management:

  • Integration: Risk profiling is incorporated into all stages of strategy development, action planning, and delivery.
  • Ownership: Each risk is assigned a responsible owner, with clear lines of accountability through the governance structures.
  • Transparency: Risks, mitigation strategies, and contingency plans are to be regularly reported to senior leadership, partnership boards, and, where appropriate, the public. 
  • Adaptability: Risks are reviewed quarterly, with the register updated in response to new information, changing circumstances, or emerging challenges.

Initial risk modelling 

An initial risk register has been developed for the objectives and key actions under each of the big moves within this strategy. Risks have been assessed for likelihood and impact, with mitigation and contingency plans agreed for high-priority areas.

Intervention 

Aims to unlock housing supply, raise standards, deliver mixed tenure & specialist housing, tackle market failures.

Risk register
Risk Description Likelihood Impact Mitigation Strategy Contingency Plan Owner
Delays in local plan adoption/ planning approvals/land assembly Medium High Early engagement, pre-app advice, pipeline review, planning performance agreements, Statements of Common Ground (SoCG) on Local Plan (LP) Reprioritise sites, phased delivery Programme Lead
Insufficient affordable housing contributions Medium High Enforce quotas, negotiate with developers Use council land/ CPO, direct delivery Housing Policy
Weak market appetite for brownfield / specialist development due to viability challenges Medium High Package sites, incentives, partner engagement Council-led delivery, joint ventures Regeneration
PRS landlord resistance to standards High Medium Education, enforcement, landlord forums Targeted enforcement, legal action Private Housing
Persistent long-term empty homes Medium Medium Taskforce, incentives, public campaigns CPO/enforcement powers Asset Mgmt/ Hsg

Investment

Aims to accelerate delivery of new/affordable/specialist homes, upgrade energy efficiency, reduce homelessness.

Risk register
Risk Description Likelihood Impact Mitigation Strategy Contingency Plan Owner
Funding shortfalls (grants, investment) Medium High Robust business cases, diverse funding sources Adjust scope, pace, seek alternative finance Finance/ Programme
Construction/retrofit skills shortages High Medium Local skills pipeline, apprenticeships, partnerships Regional contractors, adjust timelines HR/Delivery Lead
Cost inflation (materials/labour) Medium Medium Fixed-price contracts, contingency budgets Value engineering, phase nonessentials Finance Lead
Delays to regeneration pipeline Medium High Regular pipeline review, crossteam working Reprioritise, reallocate resources Asset Mgmt/ Regeneration
Failure to meet targets for larger/ accessible homes Low High Locality-based needs mapping, monitor delivery Commission additional units, reallocate Business Intel/ Hsg
Homelessness reduction targets not met Medium Medium Enhance prevention, monitor trend, partner with VCS Temporarily increase TA stock, escalate Homelessness Lead

Inclusive growth

Aims to empower residents, reduce inequalities, co-produce solutions, improve public spaces, link housing to jobs.

Risk register
Risk Description Likelihood Impact Mitigation Strategy Contingency Plan Owner
Community disengagement/ resistance Medium Medium Early & ongoing engagement, co-design, VCS partners Mediation, enhanced comms, adjust approach Community Cohesion
Skills programmes fail to attract/retain participants Medium Medium Targeted outreach, incentives, employer links Expand eligibility, partner with colleges HR/Skills Lead
Co-production not embedded in major schemes Medium Medium Set policy requirements, monitor, report Adjust procurement, increase engagement Housing/Care Leads
Public realm upgrades delayed or underfunded Medium Medium Map priorities, secure dedicated funding Phase projects, seek external grants Asset Mgmt/ Leisure
EDI priorities not addressed in engagement/ planning Low High Monitor participation, targeted outreach Commission reviews, adapt plans EDI/Comm. Building

Integration

Aims to strengthen governance, data-sharing, partnerships, and cross-sector delivery.

Risk register
Risk Description Likelihood Impact Mitigation Strategy Contingency Plan Owner
Multi-agency/partnership governance breakdown Low High Clear TOR, regular meetings, shared KPIs Escalate to senior leadership, restructure Strategy Lead
Data integration delays/ inaccuracies Medium High Invest in IT systems, regular audits, training Manual reporting, external data support Business Intel/IT
Poor attendance/engagement in partnership boards Low Medium Set expectations, regular reminders, feedback loops Update membership, increase incentives Board Secretariat
Policy misalignment between council and partners Medium Medium Regular policy review, joint working groups Escalate issues, seek external mediation Policy Lead

Ongoing Risk Management and Review 

The risk register is reviewed and updated quarterly by the Strategic Partnership Board. High-impact risks are escalated as needed, and lessons learned from risk events are integrated into future planning and monitoring. The approach is aligned with sector best practice and the HM Treasury Orange Book. Through this structured, transparent approach to risk management, Walsall Council and its partners will maintain delivery momentum, safeguard public value, and ensure that the strategy remains responsive and resilient in the face of change.